Project Overview & Technical Narrative

Executive Engineering Summary

For West Kenya Sugar Company's greenfield facility in Naitiri, Kenya, DEC executed the complete turnkey electrical infrastructure for a 12 MW bagasse cogeneration power plant and sugar mill complex.
βœ“
Comprehensive Delivery

Engineering & EPC Scope of Work

  • Containerized Logistics & Customs Export Management from India to Kenya
  • 33kV Outdoor Grid Export Switchyard Erection & Commissioning in Naitiri
  • 12 MW Steam Turbine Generator (TG) Auto-Synchronising & Protection Panels
  • Export-Spec Trisquare Type-Tested MV & LV Switchboards Installation
  • POLYVION 33kV & 11kV Armoured XLPE Cable Network Laying
Project Client Partner
West Kenya Sugar Company Ltd (Kabras) Logo

West Kenya Sugar Company Ltd (Kabras)

πŸ“ Naitiri, Kenya, East Africa

2022-2023

Speak to Senior Engineering Team

Planning a similar industrial electrification or substation installation? Consult directly with DEC lead engineers.

Call +91 84477 52245

Partner With DEC on Your Next Plant Electrification

From 132kV/220kV substations to hazardous-area flameproof complexes, DEC provides single-source turnkey EPC accountability backed by 60+ years of proven delivery.